Cost of LivingBuilding Costs The Scottish Executive estimates Western Isles building costs to be 30% above the national average, mainly due to high transportation costs and recognises that the difference in costs may vary by up to 45% for many building projects. Ferry Costs for Transporting Goods -Prices as from 2 April 1999
(Source: Caledonian MacBrayne, March 1999) Comparison of Prices for Building Materials:
|
|||||||||||||||||||||||||||||||||||||||||||
|
Steel reinforcement per Tonne |
Ready Mix concrete p/m3 |
Common concrete blocks per 1000 |
Ply veneer interior door per door |
900mm x 600mm paving slabs each |
|
|
Stornoway |
£900 |
£88 |
£240 |
£36 |
£5.24 |
|
Inverness |
£638 |
£46 |
£132 |
£19 |
£3.00 |
|
Variance in price Stornoway: Inverness |
41% |
90% |
82% |
90% |
75% |