From the start date in early July, construction of the new office in Uist has progressed apace.
As at Monday 8th.September 2008 the office building is completely closed in:
- Roof works complete except guttering to meeting room extension.
- All windows and external doors (Upvc) installed.
- Blockwork to all elevations 90% complete.
- Insulation fitted to external timber frame.
- Electrical first fix 100% complete
- Plasterboard to perimeter wall elevations in progress.
- Internal partitions being erected and lined with plasterboard consecutively.
- Plumbing first fix due to start next week.
- Ames taping scheduled for end of September but probably sooner.