|
A Report was
submitted by the Director of Finance to provide Members with an update on the
progress of the 2006/07 Capital Programme at 30 June 2006.
The Report
stated that Forecast Capital Expenditure in 2006/07 was expected to be
£31.6m. This compared with £30m achieved in 2005/06. If this level of expenditure was achieved
it would require the acceleration of resources from 2007/08, as it was £3.8m
above available resources.
At 30 June
2006 19.46% of the forecast expenditure for the year had been achieved. The
summary of expenditure was shown in Appendix 2, to the Report and the Report
stated that the detail per Committee is available in the August Information
Bulletin and on the Comhaile’s intranet.
It was agreed to recommend that, in so far as the
Committee’s interests were concerned the Comhairle approve the Forecast
Out-turn as the Revised Approved Programme for 2006/07 and specifically
approve:
(1) in the Education Capital Programme,
slippage of £837k, including:
£209k in the Boiler
Plant Replacement Programme
£50k in the Schools
Accessibility Programme
£100k in the Water
Services Improvement Programme
£53k in the Window
Replacement Programme
£83k in the Toilet
Improvement Programme
£67k for Energy
Improvements in Sir
E Scott
School
£100k for Structural
Improvements to Schools
£50k for Traffic
Management
£60k for HORSA
Replacement
£65k for Safer School
Playgrounds;
(2) in
the Environmental Services Capital Programme, acceleration of £22k in the ACE
grant scheme;
(3) in
the Transportation Capital Programme, acceleration of £263k in the Spinal Route
project and £3k for Amenity lighting; slippage of £529k for work on the North
Ford Causeway and £110k on Alternative Energy Projects;
(4) in
the Arts and Leisure Capital Programme, slippage of £87k for work at Lews Castle
and £60k for work to play areas;
(5) in the Policy and Resources Capital
Programme, slippage of £61k in work to the Comhairle Offices.
|