Aird Mhor - 8 December 2001

Breakwater core and armouring being placed
Breakwater core and armouring being placed

In the fortnight between November 25 and December 8, progress continued on the completion of the roadbed, the breakwater and the berthing facilities at Aird Mhor.

The breakdown of progress is as follows:

Roadway:

Breakwater:

Slipway concreting is complete
Slipway concreting is complete

The core and armouring was being placed to finished level working back from the end. Overall, the breakwater was between 90 and 95 per cent complete by volume.

Terminal area:

There were four tracked excavators and two articulated dump trucks on site.

Personnel: 19 total of which 9 are resident in the Western Isles