Council Logo - Link to Home Page

Sound Of Barra Integrated Transport Project

Aird Mhor - 11 September 2001

Work in progress on approach road
Work in progress on approach road

Progress on the Sound of Barra ferry project between August 12 and September 11 included:

Foreman and Engineers' site offices, canteen and compound set up at Aird Mhor

Offices set up at Ardveenish

Pilot road constructed throughout the works

Access road formed between rock source and breakwater

Soil and peat stripping to approach road, marshalling area and rock source substantially complete.

Work in progress on approach road
Work in progress on approach road

Drilling continues using two drilling rigs, one on the approach road and one in the rock source

Six more blasts took place for work on the access road

Excavating rock continues:rock being placed in pilot road and armour being sorted and stockpiled for use in breakwater.

Delineation fencing has been erected for three areas which have been identified as otter bathing pools and otter holts.

Delineation fencing has been erected to two archaeological sites adjacent to the works.

There are three tracked excavators and two articulated dump trucks on site.