Sound Of Barra Integrated Transport Project
Ard Mhòr Ferry Terminal Construction
| 23/02/02 | Final surfacing work underway |
| 14/02/02 | Completion of roadwork earthworks |
| 30/01/02 | Latest photographs |
| 29/01/02 | Work on Timber Alignment / Berthing Structure |
| 19/01/02 | Work on roadbed and associated services |
| 12/01/02 | Arrival of mobile concrete pump and a 35-tonne crawler crane |
| 22/12/01 | Breakwater core and armouring completed |
| 08/12/01 | Slipway concreting completed |
| 24/11/01 | Breakwater nearly 85 per cent complete by volume |
| 10/11/01 | Access road close to completion |
| 27/10/01 | Breakwater to be extended |
| 15/10/01 | Slipway concreting started |
| 29/09/01 | Cofferdam has been constructed |
| 18/09/01 | Work on Approach Road and Breakwater |
| 11/09/01 | Work on Access Road |
| 21/08/01 | Full-scale work begins |