Sound Of Barra Integrated Transport Project
Ceann a Gharaidh - 16 December 2000
16 December 2000
Marshalling Area: blasting and excavating in progress - 75 per cent complete
Breakwater: core filling - 200m (of 220m) into sea at low level; rock armouring in progress
Access Road: filling in progress along shore
9 December 2000
Marshalling Area: blasting & excavating in progress - 65% complete
Breakwater: core filling 190m (of 220m) into sea at low level; rock armouring in progress
Access Road: filling in progress along shore
2 December 2000
Marshalling Area: excavating was approximately 60% complete.
Breakwater: core filling 170m into sea at low level; rock armouring in progress
Access Road: filling in progress.