Sound Of Barra Integrated Transport Project
Ceann a Gharaidh - 26 May 2001
26 May 2001
Slipway: concrete works completed
Timber Alignment Structure: Timber alignment structure and fenders completed
Services: Services along access road continuing
19 May 2001
Slipway: concrete works 90% completed
Timber Alignment Structure: Timber alignment structure and fenders completed
Services: Services along access road continuing
12 May 2001
Slipway: concrete works 80 per cent complete
Timber Alignment Structure: Timber alignment structure and fenders completed
Services: Services along access road continuing; laying started from road junction
5 May 2001
Slipway: divers on site for underwater concreting of walls and slab; full length of berthing wall concreted; toe beam concreting begun - complete; slab concreting - 40 per cent complete
Timber Alignment Structure: fender pile bases - 8 cast (of 9); fenders, timber piles and timber structure - 60 per cent complete