Sound Of Barra Integrated Transport Project
Ceann a Gharaidh - 29 September 2001
Completed Terminal
29 September 2001
Surfacing of sundry works has been completed and the existing road between the South Glendale junction and the quarry haul road has been overlaid
1 September 2001
- Traffic signs have been erected
- CnES are placing navigation buoys for the new ferry route
Road Junction
6 August 2001
- Ceann a Gharaidh navigation light installed
- Continuation of remaining minor works
14 July 2001
As of July 14, the Ceann a Gharaidh and quarry reinstatement were regarded as substantially complete with minor finishing works and completion of demobilisation remaining