Sound Of Barra Integrated Transport Project
Ceann a Gharaidh - 30 June 2001
Slipway
30 June 2001
The overall round-up for the week includes:
- Roads - wearing course started in marshalling area
- Marshalling area - drainage interceptor, septic tank and soakaway installed
- Marshalling area - street lighting columns and cabling installed; footpaths continuing
- Reinstatement and landscaping works continuing
23 June 2001
The overall round-up for the week includes:
- Services along access road more than 90 per cent complete
- Reinstatement and landscaping works continuing
- Marshalling area - kerbs completed, drainage in progress
- Road and marshalling area roadbase and basecourse completed
- Pavements 70 per cent complete
Approach Road
16 June 2001
The overall round-up for the week includes:
- Services along access road over 90 per cent complete
- Parapet walls completed
- Reinstatement and landscaping works in progress
- Marshalling area - kerbs and drainage in progress
- Road and marshalling area formation completed and roadbase begun
9 June 2001
Marshalling area: Kerbs and drainage in progress
Slipway: Concrete works completed
Timber Alignment Structure: Timber alignment structure and fenders completed
Services: Services along access road over 90 per cent complete
Reinstatement works: Continuing