Sound Of Barra Integrated Transport Project

Eriskay - 3rd March 2001

Parapet walls
Parapet walls

Work on quarrying and excavation for the Causeway is closer to completion, after the work done in the week to March 3.

Causeway

Bridge section
Bridge section

Bridge

North span precast beams placed, shuttering and reinforcement fixing has commenced.

Eriskay Approach Road

Weather: Wintry showers all week; blizzard conditions on Monday with northerly winds; Temperatures below freezing at times.

Personnel: 57 total employed on site (including 2 CnES) - 60 per cent resident in the Western Isles.