Council Logo - Link to Home Page

Sound Of Barra Integrated Transport Project

Eriskay - 7th April 2001

Bridge
Bridge

Work in the week to April 7 saw the sea flowing freely once again through the bridge cut - giving Eriskay a sort of return to Island status.

But would-be mariners were warned through an advertisement in the Stornoway Gazette that the bridge opening was still being cleared of submerged rocks and that fenders were still to be attached to the bridge.

The bridge, which will give very little clearance at high tide for vessels, is mainly intended to allow the passage of aquatic creatures.

The roadway on top of the causeway is now moving rapidly towards its final shape.

Causeway
Causeway

Causeway

View of causeway
View of causeway

Bridge

Uist Quarry

Drilling, blasting & excavating rock ­ over 90 per cent complete

Road and Services

Weather: Windy early in the week becoming calmer, dry and sunny

Personnel: 56 total employed on site (including 2 CnES), 60% resident in the Western Isles.