Sound Of Barra Integrated Transport Project

Eriskay - 9th June 2001

Cutting and causeway
Cutting and causeway

The significant figures - 100 per cent - appear in the data for the week ending June 9 as work on the Causeway sweeps towards a conclusion.

A final total of 700,000 tonnes of rock has been removed from the Glendale quarry and from the Eriskay cutting and placed to form the causeway.

Reinstatement is now continuing at the quarry to restore the site.

Causeway

Bridge
Bridge

Road and Services

Weather: mild, sunny spells, prolonged showery periods

Personnel: 55 total employed on site (including 2 CnES), 67 per cent resident in the Western Isles

Completion Programme