Sound Of Barra Integrated Transport Project

Eriskay - 17th March 2001

View of causeway
View of causeway

Work on the bridge section of the causeway was almost complete in the week up March 17. Meanwhile rock armouring of the causeway was almost complete as well and workers were preparing to remove the thousands of tonnes of rock put in the Sound of Eriskay to provide the temporary causeway bypass of the bridge site while work continued.

Causeway

Bridge section
Bridge section

Bridge

Uist Quarry

Drilling, blasting & excavating rock ­ over 85 per cent complete

Eriskay Approach Road

Weather: Fine all week

Personnel: 51 total employed on site (including 2 CNES), 67% resident in the Western Isles.