Sound Of Barra Integrated Transport Project

Eriskay - 20th January 2001

View of bridge section
View of bridge section

Rock armouring to core: in progress - 60 per cent complete.

Total rock placed: 560,000 tonnes - 80 per cent of final quantity.

Uist Quarry: Drilling, blasting & excavating rock ­ 80 per cent complete.

Bridge:

View of causeway
View of causeway

Eriskay Approach Road: No work this week - rock excavation over 90 per cent complete.

Weather: fine all week, with some moderate winds.

Personnel: 52 employed on site (including 2 CnES) - 62 per cent resident in the Western Isles.