Sound Of Barra Integrated Transport Project

Eriskay - 21st April 2001

Bridge
Bridge

Work continued last week after a holiday break and several aspects of the Causeway project are almost entirely completed, with almost all the rock needed for the link having been blasted and moved.

Causeway

Bridge

Diversion fill removal - 85 per cent complete

View of causeway
View of causeway

Uist Quarry

Drilling, blasting & excavating rock Ð 95 per cent complete

Road and Services

Reinstatement works continuing

Weather: mostly fine and cold, with some wind and showers

Personnel: 53 total employed on site (including 2 CnES), 60% resident in the Western Isles.

Programme: Completion of causeway and Ceann a Gharaidh planned for end of July.