Sound Of Barra Integrated Transport Project

Eriskay - 23rd June 2001

View of causeway from Easabhal
View of causeway from Easabhal

Work on the road sytem and marshalling area for the new ferry port on Eriskay proceeded fast in the week to June as did work on the highers surfaces of the causeway road.

Causeway - Uist Quarry

Reinstatement continuing

Road and Services

Weather: wet/windy to fine/sunny

Personnel: 49 in total employed were on the site (including 2 CnES), 57 per cent resident in the Western Isles

Completion programme