Sound Of Barra Integrated Transport Project

Eriskay - 26th May 2001

Cutting and causeway
Cutting and causeway

With work on the main causeway structure almost completed, reinstatement work on the Uist quarry began in the week up to May 26 in line with the commitments to environmental restoration which were determined at the start of the project. Signs of continued progress included:

Causeway

Causeway looking south
Causeway looking south

Uist Quarry

Rock extraction for causeway completed - reinstatement begun

Road and Services

Weather: mostly dry and sunny; windy with showers at the end of the week

Personnel: 55 total employed on site (including 2 CnES), 60 per cent resident in the Western Isles