Sound Of Barra Integrated Transport Project

Eriskay - 27th January 2001

View of bridge section
View of bridge section

Steady progress has continued with the Eriskay Causeway and associated works over the week to January 27

Rock armouring to core: in progress - 65 per cent complete.

Total rock placed: 575,000 tonnes - 82 per cent of final quantity.

Uist Quarry: Drilling, blasting & excavating rock ­ 80 per cent complete.

Bridge:

Eriskay Approach Road: No work this week - rock excavation over 90 per cent complete.

Weather: stormy all week with rain and wintry showers calming at weekend.

Personnel: 51 employed on site (including 2 CnES) - 62 per cent resident in the Western Isles.