Sound Of Barra Integrated Transport Project

Eriskay - 28th April 2001

Causeway
Causeway

Almost one-third of the causeway was, by April 28, completed to the final planned level before the road surface can be put on. Other progress included:

Causeway

Bridge

Diversion fill removal, 85 per cent complete

View of causeway
View of causeway

Uist Quarry

Drilling, blasting and excavating rock - 95 per cent complete

Road and Services

Weather: mostly fine, with some wind and showers

Personnel: 53 total employed on site (including 2 CnES), 60% resident in the Western Isles.